Kennedy Highway CN11566
This project consisted of widening almost 3km of road to include overtaking lanes, wide centreline treatment and intersection upgrades.
To achieve this the project required substantial cut and fill areas, culvert extension and drainage upgrades.
The pavement was constructed using lightly bound subbase and base materials. Saturated areas required rock mattress treatments and sub soil drains.
Drainage upgrades included gabion rock baskets and rock protection.
Description: CN 11566 Kennedy Highway Section 2
Client: Department of Transport and Main Roads
Location: Kennedy Highway (32A) 27.190km-30.3km